- Name – Pungwe C Hydroelectric Power Station
- River – Chiteme river (left bank tributary of the Pungwe river), Honde Valley
- Installed capacity – 3.75 MW
- Head – 180 metres
- Penstock size – 1,200mm diameter
- Penstock length – 2,750m
- Penstock flowrate – 3m3/s
- Turbine design – Turgo turbine manufactured by Gilbert Gilkes & Gordon Ltd.